Solar Rooftop Installation Project, Building C
The Company renovated the 7th floor of Building C to be used as office space. During the renovation, a solar rooftop system was installed on the building’s rooftop to generate electricity for use within the office, such as for the air-conditioning system and office equipment. The project installed 144 solar panels with a total installed capacity of 80 kW.
Performance Results (July 1 – December 31, 2025)
- The system generated 55,204 kWh of electricity, replacing electricity from the main grid
- The estimated full-year performance is expected to reach approximately 110,408 kWh per year.